Old Street Roundabout – Wider Highway Transformation Scheme

TFL, working in close partnership with Islington and Hackney Councils, have now started work on the project to transform Old Street roundabout, making it a safer and more pleasant place for people who live, work and visit the area.

The works are in three phases:

  • Phase A 19 November 2018 Enabling Works & Site Investigations
  • Phase B March 2019 Advanced Highway Works Preparation
  • Phase C May 2019 Main Works start (Easter TBC)

Islington is working closely with TfL and Hackney Council to minimise both the disruption and the noise produced from the works.

For the most up to date information please visit the TfL website.

More information:
W: www.tfl.gov.uk/old-street-roundabout
T: 0343 222 1234
E: OldStreetroundabout@tfl.gov.uk
TFL Public Liaison Officer for Old Street Works: David.Kingston@morgansindall.com
Travel news: @TFLBusAlerts @TFLTrafficNews @TFLTrafficAlerts

Old Street Iconic Gateway project:

Separate work is progressing to develop a design for an ‘Iconic Gateway’ to dovetail with the highway transformation work.

For information on the Old Street Iconic Gateway public space design process, please visit our page in the planning area. 